Thursday, February 24, 2011

Good News and Bad News

The good news is that the design of the roof and wall are completed. Eugene, our design lead, emailed out the designs and by the pictures and complicated numbers it looks like the schoolhouse will be ready to withstand any rainstorm, hurricane or earthquake. The bad news is that during the meeting we did cost estimates on the material and found out that we would need a lot of material that obviously requires a great deal of money. Our previous project was the latrines that did not require as much material as a schoolhouse so the costs of materials gave us somewhat of a jolt. Of course we are building the schoolhouse in stages so this way, we can raise the money needed as each stage approaches. If you want to check out the layout of the schoolhouse, they can be viewed through our Google Groups page (see attached link below) listed under discussions as EWB Schoolhouse- Building Layout and Alternatives.